First of all, it's not a claim it flew like that. Only that the tarmac expo/debut was like that. Oliver adds that the 1st test flight was supposed to happen 2 months after that. And he also says that the 1st test flight was also delayed, although doesn't say by how much.
Anyhow, Jon Ostrower is a real journalist who was later with the WSJ. As al-Jazeera detailed in 2014:
“What I realised walking around it is that you could look up in the wheel well and you could see daylight coming through the cabin,” says Jon Ostrower, now of the Wall Street Journal. “Studying photos later on, I realized the doors were made of plywood. The airplane just wasn’t finished.”
At the time, Ostrower was a young aviation blogger working for Flight International Magazine. He didn’t get the chance to attend with the rest of the media. He was there as the guest of a Boeing engineer who liked his blog. So while the other reporters were busy filing stories, Ostrower was spending time with the plane. “During that hour, I had a chance to really kind of study it. Without any chaperone or minder or anything, I just had a chance to really kind of just study the details. And it wasn’t done,” says Ostrower.
Anyhow, the tarmac expo was quote incomplete inside, as another witness said:
“Anybody, even a rank amateur, could have walked — well, they couldn’t have walked through the airplane because there weren’t even floorboards to stand on.” says Kevin Sanders, an employee at Boeing for 30 years. “But if they could have walked through it, they would have seen that there were no systems, there was no environmental control system, no wiring, no hydraulics, no plumbing. There was nothing.”
And story goes that they took it apart and put it back together:
Inside the factory, there was a scramble to salvage the situation. Hours after the rollout, the plane was in pieces. “Every panel came off the airplane. It got taken off its landing gear. The tail was taken off. It was a mad dash. It was an absolute mad dash to the first flight,” says Jon Ostrower.
Anyhow, details aside, a paper notes that:
In reality, the development of the Dreamliner was a disaster – the first flight was delayed by 26 months and the first delivery was delayed by 40 months. [...]
We shall start by examining the status of the first “assembled” Dreamliner (LN 1) rolled out for the 787
premiere in July 2007. Unknown to the public at the time, the plane was a hollow shell, even some of the outer structure is fake, e.g., the wing slats are painted wood (Turim and Gates 2009). [...]
- LN1 primary structure is not completed by August 2008
Indeed a quick search shows that the 1st flight didn't happen until Dec 2009.
"Turim and Gates" refers to this timeline:
2007 January: A Wall Street analyst says the 787 program is running into delays and cost increases. CEO Jim McNerney says the plane is on target for its first test flight around the end of August 2007 and first delivery in May 2008.
May: Boeing shows media the first 787 starting to come together in Everett.
June: Boeing engineers assembling the forward section of Dreamliner No. 1 find a 0.3-inch gap at the joint between the nose-and-cockpit section and the fuselage section behind it, made by different suppliers. Engineers fix the distortion by disconnecting and reconnecting internal parts that brace the frame.
Reports surface at the Paris Air Show that the 787 is up to four months late. Boeing says the first test flight may slip to September 2007, with the jet still on schedule for first delivery in May 2008.
July: The first assembled 787 is rolled out in front of 15,000 employees and customers at Everett, with live global satellite feeds and much hoopla. But unknown to the worldwide audience, the plane is a hollow shell. And even some of the outer structure is fake: The wing slats are painted wood.
Once back in the factory, the airframe is partially disassembled. Extensive rework is required because the plane was put together with temporary fasteners in the airframe and major systems weren’t installed.
July 25: Boeing shares hit an all-time high of $107.80, boosted by strong 787 orders. The company admits the plane is running slightly behind in certain areas but holds to its schedule.
October: Boeing acknowledges a delay of up to six months — the worst delay to a jet program in the company’s history — due to problems in unfinished work passed along by its global partners and delays in finalizing the flight-control software. The new schedule puts the first flight in March 2008 and the first deliveries late that year. Mike Bair, 787 program head, is replaced by Pat Shanahan from Boeing’s defense unit.
November: Ousted program head Bair admits the 787 supplier partners let Boeing down, saying, “Some of these guys, we won’t use again.
2008 January: A further three-month delay is announced due to problems with unnamed 787 suppliers and slow assembly progress at the Everett plant. First flight is moved to June 2008 and first delivery to early 2009, putting the plane about nine months behind its original schedule.
April: Boeing confirms yet another six-month delay due to continuing problems with unfinished work from suppliers. The first delivery is pushed to the third quarter of 2009 — about 15 months behind the original schedule. Some of the largest 787 customers’ planes will be at least two years late.
September: A second Machinists strike begins at Boeing, lasting 57 days. The company struggles for a month afterward to get production back on track.
November: News emerges of a new, embarrassing and serious problem. About 3 percent of the fasteners put into the five test airplanes under construction in Everett were installed incorrectly and must be removed and reinstalled.
December: Boeing acknowledges another six-month delay for the 787 and reorganizes management again. Shanahan is put in charge of all commercial-airplane programs and brings in Scott Fancher from Boeing’s military side to take the day-to-day lead on the 787. The first Dreamliner is now scheduled to fly sometime between April and June of 2009, with first delivery to ANA sometime in the first three months of 2010.
2009 January-February: Facing a sharp industry downturn, Middle East leasing company LCAL and Russian airline S7 Group cancel orders for 37 Dreamliners. Many other customers push back their 787 delivery dates.
May: Dreamliner No. 1 moves out to the flight line, scheduled for first flight in June.
Late in the month, Boeing engineers working on the ground-test airplane find a structural defect at the wing-body joint. The problem is not made public during weeks of analysis that follow.
June: At the Paris Air Show on June 15, Boeing commercial-airplanes CEO Scott Carson says the plane is on schedule to fly by month’s end. The following week, Boeing engineers decide the structural flaw must be fixed before the plane flies. On June 23 Boeing stuns the industry by postponing the first flight indefinitely.
July: Engineers begin work on a fix for the wing-body joint flaw.
August: Boeing’s new schedule calls for first flight by year’s end, with first 787 delivery by the end of 2010.
Four days later, Scott Carson steps down as chief executive, replaced by Jim Albaugh, previously chief executive of Boeing’s defense and space division.
[...] November: Boeing breaks ground in Charleston, S.C., for a 750,000-square-foot complex.
Boeing mechanics complete the wing-body joint fix. Engineers repeat the wing stress test, and the Dreamliner gets the green light to fly.
December: After a repeat of engine and system tests and a series of taxi tests on the ground, the first flight is scheduled.
So yeah, this plane had serious delays, in part due to core structural problems. The mockup launch with some wood parts is not all that improbable given the other details, and that it only flew for the first time 2 years after that ground show.